EEC reported that overtime is projected to fall by 38 per cent in 2027/28, provided planned maintenance is fully funded. It said it saved E149 million through smarter power purchasing. Staff numbers will remain flat at 1 042 in both years.
Electricity losses stand at 12.61 per cent, within the target of 12.68 per cent. The time taken to collect amounts owed by customers has improved to 48 days, from 56 days. No new projects were started in 2026/27 due to cash constraints.
Those measures are material, but they do not resolve the fiscal question at the centre of the application. A utility that saves E149 million on purchasing and cuts E99.9 million in operating expenditure can still record a shortfall of E449.7 million if E333.5 million in expected government support does not arrive. That is a structural risk, not an operational failure.
With that being said, Stromvig said customers were entitled to ask what improvement they would see in return for paying more. She said EEC’s responsibility was not simply to recover costs, but to ensure that available resources supported safer, more reliable and more responsive electricity service.
EEC-Acting-Managing-Director-Candy-Stromvig-making-her-remarks-during-her-first-appearance.
Add a Comment